What is difference between Upgradation Project and Rollout Project?

posted May 15, 2011, 7:36 PM by Sen Long   [ updated May 15, 2011, 8:26 PM ]

Upgrade:
You take your current SAP solution and upgrade it to a never version ,example is ECC4.7 -> ECC6.0
Upgrade = You DO not increase scope You upgrade something you already have to a never version

Roll-out:
There is several scenarios;
(a) You use SAP but wants to increase functional scope
you build a new SAP template or enhance your current SAP template and you roll that out to your existing organisation
(b) You use SAP but wants to organizational scope
You take your existing SAP template and applies it to additional organizational units (Company codes)
(c) You do not have SAP but wants to start using SAP


SAP provides two different ASAP templates depending if it is a Global or local roll-out